Tuesday, 19 May 2015

Enterprise Calendars Use Case

Applies: Project Server 2007+

Here are a few considerations when working with Enterprise Calendars. Enterprise Calendars can be assigned to Projects, Resources and Tasks.

image

1) Project Calendar

An Enterprise Calendar assigned to a Project impacts all the Tasks within the project schedule. E.g. tasking will NOT take place on weekends etc.

Note: ensure that the project scheduling OPTIONS for task working times match that of the project calendar.

PMO will need to keep this Enterprise Calendar updated for exceptions such as weekends, public holiday etc.

 

2) Resource Calendar

Resource Calendars are based on a specific Enterprise Calendar, normally the BASE calendar that the project is based on, so that it inherits the exceptions such as weekends, public holiday etc.

(+)

Resource Managers/PMO can add further exceptions to the resource calendar for specific resource availability/exceptions e.g. holidays etc.

Note: if a Resource calendar is based on a different BASE calendar to that of the project, then the resource calendar scheduling will take precedence. E.g.  an international Project is based on UK holidays and Resource in Middle East is based on UAE calendar (with Friday/Sat off and Sun working). Any task that has the UAE resource assigned will show as working on Sunday. The scheduling for the assigned task  is governed by the working times of the resource on that task, i.e. based on that resource’s calendar (BASE Calendar + exceptions).

 

3) Task Calendar

If you want to override the default scheduling behaviour of resource calendar, then you will need to set the scheduling exception against the task and assign a different/specific calendar. See figure below to override the Resource Calendar scheduling.

SNAGHTML22c7a0

Note: if you want to update multiple[le task calendars en-mass, inside of a project,  you can insert the following two columns/built in fields. And then Copy/fill-down to all the tasks in the project. Alternatively, you can write a macro and add to Enterprise Global, to do this for programmatically.

image

Hope this helps.

Wednesday, 6 May 2015

SharePoint Server 2016 update

Today, Microsoft confirmed that SharePoint Server 2016 will become generally available in Q2 2016, with a public beta planned for Q4 2015, and commitment to delivering on-premises releases of SharePoint for the foreseeable future. There will be support for combination of on-premises, cloud and hybrid deployments for many years to come.  Learn More>>