The definition of Current tasks should be in-progress, overdue and assignments due to start within set number of days as configured by administrator.
Consider a scenario, where a task/assignment in My Tasks is completed. This is done either by the Project Manager (owner) directly in the plan or the team member via collaborative task updates. When you next navigate to PWA > My Tasks to view current tasks, you will see the competed assignment. Over time, this list will get longer and longer as the number of projects are completed. Now, imagine if your business processes involved EPM timesheeting. When you Add Lines, your list will look enormous.
(click picture to enlarge)
Best Practises for dealing with this issue
Here are some of the best practice step when completing tasks/activities.
After updating the project with actuals (or % complete), Project Managers/Owners should;
- Set the ‘Publish’ flag for completed tasks to ‘No'. Note: use built-in filter to quickly identify completed tasks.
- Save Project
- Publish project
- File > Close and Check-in
(click picture to enlarge)
Doing this will stop the completed Tasks from appearing in My Tasks and My Timesheets. voilà…..sorted!!
It does involve a structured approach to ‘closing’ completed project activities/tasks but it pays off in the end.
Note: The alternative is to set the Project Resource ‘Booking Type’ to ‘Proposed’. I would not recommend this as this conflicts with Resource Management processes.